Renewables

McDermott Executes Record-Breaking Lift on BorWin6 Project

McDermott has safely and successfully executed its heaviest stacking lift at its Jebel Ali fabrication yard in Dubai. This record-breaking achievement marked the latest milestone on the BorWin6 980MW high-voltage, direct current (HVDC) project for TenneT.

The stacking of deck level one had a total weight of 1,962 metric tons (MT) and was conducted in a tandem lift operation involving six cranes. This complex operation was executed by McDermott's lifting fabrication team, alongside construction support engineering, and its health, safety and environmental team. The lift was performed securely and ahead of schedule.

"Jebel Ali is unrivalled in its ability to deliver complex offshore structures," said Rob Shaul, McDermott's Senior Vice President, Low Carbon Solutions. "We are well positioned to continue driving execution excellence throughout the remainder of the construction phase, while maintaining the project's impeccable safety record."

Awarded in 2022, BorWin6 is a key part of McDermott's growing energy transition portfolio and represents the company's first project in the thriving offshore wind market. McDermott is delivering engineering, procurement, construction, installation and commissioning services, through a consortium with GEIRI / C-EPRI, for an HVDC offshore converter platform, located offshore Germany.

Offshore Source Logo

Offshore Source keeps you updated with relevant information concerning the Offshore Energy Sector.

Any views or opinions represented on this website belong solely to the author and do not represent those of the people, institutions or organizations that Offshore Source or collaborators may or may not have been associated with in a professional or personal capacity, unless explicitly stated.

Corporate Offices

Technology Systems Corporation
8502 SW Kansas Ave
Stuart, FL 34997

info@tscpublishing.com