Successful Mooring System Installation for Jumbo in Egypt

The Fairplayer and her team have successfully completed the pre-installation and tensioning of a shallow water CALM buoy mooring system at a depth of 26 meters for the Mersa El-Hamra terminal offshore Egypt.

Scope of Work

Jumbo’s scope included the pre-lay of 10 Stevshark drag anchors and 6 chain moorings and the subsequent tensioning of the mooring legs up to 512 tonnes, for our client WEPCO / Micoperi.

IMG 20190430 205117 HHTPlanning & Preparation

With a short lead time, the project team managed to professionally prepare for the full scope of work and provide the required project procedures, equipment and personnel on-time.

Jumbo would like to thank the specialized teams who contributed towards making this project possible. We look forward to our next offshore mooring installation!

Offshore Source Logo

Offshore Source keeps you updated with relevant information concerning the Offshore Energy Sector.

Any views or opinions represented on this website belong solely to the author and do not represent those of the people, institutions or organizations that Offshore Source or collaborators may or may not have been associated with in a professional or personal capacity, unless explicitly stated.

Corporate Offices

Technology Systems Corporation
8502 SW Kansas Ave
Stuart, FL 34997

info@tscpublishing.com