DEME Awarded Contract for OranjeWind Offshore Wind Farm

DEME has been awarded a substantia contract to carry out the transport and installation works for the inter-array cables and secondary steel for the OranjeWind offshore wind farm in the Netherlands. With an installed capacity of nearly 800 MW, the wind farm is being developed by a joint venture of leading energy companies RWE and TotalEnergies.

DEME will transport and install a total of 114 km of inter-array cables, which will connect all 53 foundations to the offshore substation in the Dutch North Sea. The extensive scope includes all the engineering, preparation and supporting activities, ensuring that DEME will deliver a complete solution to RWE and TotalEnergies.

Pre-sweeping will be conducted at the wind farm, situated 53 km from the Dutch coast, before cable installation in areas with significant sand waves to ensure the cable is buried at the required target depth. At the offshore substation and crossings of existing assets, the cables will be stabilized with rock. The secondary steel scope includes the transport and installation of boat landings, access platforms and internal platforms at the monopile foundations.

Scheduled to start in the second half of 2026, DEME will deploy offshore and cable installation vessels, a hopper dredger and fallpipe vessel, as well as additional supporting equipment.

Offshore Source Logo

Offshore Source keeps you updated with relevant information concerning the Offshore Energy Sector.

Any views or opinions represented on this website belong solely to the author and do not represent those of the people, institutions or organizations that Offshore Source or collaborators may or may not have been associated with in a professional or personal capacity, unless explicitly stated.

Corporate Offices

Technology Systems Corporation
8502 SW Kansas Ave
Stuart, FL 34997

info@tscpublishing.com