Oil & Gas News

Visual Observation Inside South Timbalier 220 Well

The Bureau of Safety and Environmental Enforcement (BSEE), U.S. Coast Guard, and Walter Oil & Gas Corporation (Walter), through the Unified Command, continue to hercules 265-oversee and coordinate response efforts to secure the South Timbalier 220 natural gas Well A-3. Safety of personnel and protection of the environment remain the top priorities.

All debris is now removed from the wellhead giving crews vertical access to the well, removal was done from the derrick barge “Performance”.

BSEE approved plans to send a camera and logging tools down the wellbore and is conducting visual observation along with Unified Command. Observations will be used to advance well intervention plans. No gas releases are reported from fixed wireless detectors placed some 30 feet from the top of the well or detection devices carried by all onsite personnel.

Drilling on the relief well is underway using the Rowan EXL-3 jack-up rig, contracted by Walter. Drilling is expected to continue through early September. Many factors can affect the expected schedule including weather and the intricate work of locating the target well bore at the end of the drilling process. A relief well is drilled to intercept the target well. Once intercepted, drilling mud, followed by cement will be pumped into the well to secure it.

All available options to safely secure the natural gas well remain under consideration. Work is moving forward on all approaches.

From visual observation, a sheen is no longer present in the area of the well. The Coast Guard continues to maintain a 500-meter safety zone around the site. Firefighting and other marine vessels remain onsite with personnel from Walter, Hercules, and other professional engineering contractors, and relevant federal agencies. BSEE's investigation into the cause of the loss of well control continues in coordination with the Coast Guard.

Additional updates will be issued as information becomes available. Media inquiries and requests for additional information should be directed to. 504-736-2595.

BACKGROUND:  Walter experienced a loss of control of Well A-3 at approximately 8:45a.m. July 23 on an unmanned platform at South Timbalier Block 220 while doing completion work on the sidetrack well to prepare the well for production. The operator reported the safe evacuation of 44 personnel from the Hercules 265 jack-up rig. Coast Guard confirmed that the leaking natural gas ignited at 10:45 p.m. CDT July 23. BSEE confirmed July 25 that the well flow subsided after a natural bridging process and the fire was suppressed.

.
Offshore Source Logo

Offshore Source keeps you updated with relevant information concerning the Offshore Energy Sector.

Any views or opinions represented on this website belong solely to the author and do not represent those of the people, institutions or organizations that Offshore Source or collaborators may or may not have been associated with in a professional or personal capacity, unless explicitly stated.

Corporate Offices

Technology Systems Corporation
8502 SW Kansas Ave
Stuart, FL 34997

info@tscpublishing.com