Jumbo Ships Large TP’s for First Offshore Windfarm in Taiwan

Jumbo has just completed the shipment of the heaviest, tallest and the largest diameter Transition Pieces (TP’s) the company has ever transported.

These TP’s were shipped for Jan De Nul Group in cooperation with brokers Multi Marine Chartering B.V. from Laem Chabang to Taichung, where they will form part of Taiwan’s Formosa 1 Phase 2 Offshore Wind Farm (OWF).

The Formosa 1 OWF will have a total capacity of 128MW once built and commissioned. Phase 1 of Formosa 1 features two Siemens 4MW demonstration turbines, the first ever wind turbines to be installed off Taiwan. The Formosa 1 Phase 2 is owned by Formosa I Wind Power Co. Ltd., a partnership of Ørsted (35%), JERA (32.5%), Macquarie Capital (25%), and Swancor Holding (7.5%).

2 JumboJumbo Value

In advance of the shipments, Jumbo coordinated the fabrication of 12 grillages which act as individual secure holdings on deck for each TP. After installing the grillages on board the Jumbo Kinetic, the vessel set sail to Laem Chabang to set the project in motion.

The TP’s were carefully secured to the grillages on board the Jumbo Kinetic by her specialized team and then moved in 3 shipments from Laem Chabang to Taichung. In total 20 TP’s with a diameter of 7,8 x 30 m high and a weight of 462 tonnes each were shipped.

3 JumboJumbo Reliability – Smart Shipping. No Surprises.

Inventive yet safe and efficient ways to ship and install cargoes of all shapes and sizes are engineered on a daily basis by the Jumbo team. For this project, Jumbo’s project manager, engineers, vessel manager, commercial, procurement, crewing, QHSE, technical departments, crew and port captains worked closely with the broker and their client to ensure the loading and discharge operations were successfully and safely executed on-time for all three shipments. The added complexity of the height and weights of the TP’s meant that smart and accurate logistical and operational planning and engineering were required.

At the end of the project, Jumbo’s Project Manager arranged another unique solution for their client by lending-out two of our grillages in order to create extra shore storage locations for the TP’s.

Offshore Source Logo

Offshore Source keeps you updated with relevant information concerning the Offshore Energy Sector.

Any views or opinions represented on this website belong solely to the author and do not represent those of the people, institutions or organizations that Offshore Source or collaborators may or may not have been associated with in a professional or personal capacity, unless explicitly stated.

Corporate Offices

Technology Systems Corporation
8502 SW Kansas Ave
Stuart, FL 34997

info@tscpublishing.com